Sorry | Bid Closed [ Back ] |
We work with organizations around the world to help poor and vulnerable people overcome emergencies, earn a living through agriculture and access affordable health care.
Name of Tender : Rehabilitation and Upgrading of Hand-Dug Well to Water Yard in (Jokosti village-Central Jebel Mara Locality-Central Darfur State)
Tender Number: RFQ-CD-SD400003-2024
Opening Date : 12th of March 2024
Deadline Submission date: 18/March. /2024 – 12 :00 PM Please submit your bid to this email only.
Please submit your bid to CRS Zalingei tender box or through email: tenders.sudan@crs.org
|
اسم العطاء: إعادة تأهيل وتحديث بئر محفورة يدويا و ترفيعها إلى محطة مياه في (قرية جوكوستي – محلية وسط جبل مرة - ولاية وسط دارفور)
رقم العطاء: RFQ-CD-SD400003-2024 تاريخ بدء العطاء : 12مارس 2024
تاريخ انتهاء التقديم:18 مارس /2024– 12:00 بعد الظهر
الرجاء ارسال عرضكم الي مكتب الاغاثة الكاثلوكية مكتب بزالنجي وعن طريق الايميل الالكتروني tenders.sudan@crs.org
|
Dear Sir / Madam, CRS Sudan is looking for companies to provide the items/services shown in Attachment 1 at a competitive price and with high quality.
General Requirements 1. Must Be Registered to conduct the business and in compliance with federal governments tax regulations in Susan. 2. Experience supplying International Organizations, Non-Governmental Organizations, or large private companies will be an advantage. 4. CRS retains the right to reject, cancel, negotiate, amend, split and accept any offer, without consideration of the lowest offer. 5. This is an invitation to vendors and is not a promise or obligation that CRS will contract with suppliers through the submitted offers. 6. Relevant bid committee may request for physical samples of some items during evaluation process of bids. |
سيدي / سيدتي العزيز(ة) هيئة الإغاثة الكاثوليكية برامج السودان تبحث عن شركات من المهتمين بتوفير المواد/ الخدمات المشار إليها أدناه في الملحق رقم 1 بأسعار منافسة وبجودة عالية.
متطلبات عامة: 1 . يجب أن يكون مسجلا لإجراء الأعمال التجارية مع ما يتوافق ولوائح الضرائب الحكومية في السودان . 3 . الخبرة في تزويد المنظمات الدولية، المنظمات الغير حكومية، أو الشركات الكبيرة الخاصة ستكون ميزة. 4 . تحتفظ هيئة الاغاثة الكاثوليكية بالحق في رفض، إلغاء، التفاوض، تعديل، تجزئة وقبول أي عرض، دون النظر الى أدنى عرض. . 5. هذه دعوة للموردين وليس وعد أو التزام من هيئة الإغاثة الكاثوليكية للتعاقد مع الموردين من خلال العروض المقدمة 6. قد تقوم لجنة الإحالة المعنية بطلب نماذج عينية لبعض المواد اثناء عملية تقييم العروض. |
Payment Terms
|
شروط الدفع
|
Acceptance of Payment Terms Do you accept the above payment terms?
|
الموافقة على شروط الدفع: هل توافق على شروط الدفع اعلاه:
|
Requested Information The submission must include:
|
يجب تقديم ما يلي: يجب ان يتضمن التقديم ما يلي :
|
Bid Requirements Offers that do not meet the following will be automatically rejected regardless of price:
|
معلومات ملء العطاء سوف يتم رفض أي عطاء لا يلتزم بالشروط أدناه بغض النظر عن السعر:
|
Delivery Instructions: Complete and stamped and signed offer can be submitted through CRS Zalingei office or by email to tenders.sudan@crs.org
|
تعليمات التسليم: يجب تقديم العطاء الكامل والمختوم و الموقع عن مكتب المنظمة بزالنجي او طريق عنوان البريد الالكتروني tenders.sudan@crs.org
RFQ-CD-SD400003-2024 وإلا سيتم استبعاد العطاء. يجب ان لا يتجاوز حجم المرفق 15 ميجابايت على ان لا تتجاوز السيرة الذاتية للشركة اكثر من 10 صفحات.
|
Experience Reference List
قائمة مراجع الاعمال السابقة
S/N |
Name of Organization أسم المنظمة |
Name of Person أسم الشخص |
Name of Project أسم المشروع |
Project Start Date تاريخ المباشرة بالمشروع |
Project duration مدة تنفيذ المشروع |
Phone Number رقم الموبايل |
Email Address البريد الالكتروني |
1 |
|
|
|
|
|
|
|
2 |
|
|
|
|
|
|
|
3 |
|
|
|
|
|
|
|
4 |
|
|
|
|
|
|
|
Company name: أسم الشركة : |
|
Legal address: العنوان الثابت: |
|
Telephone Number: رقم الهاتف: |
|
Email: عنوان البريد الإلكتروني: |
|
Representative Name اسم الممثل: |
|
Business Certificate Registration Number: رقم تسجيل شهادة العمل: |
|
Tax registration Number: رقم التسجيل الضريبي: |
|
Contract duration: مدة العقد : |
|
Do you have partnerships with any other companies (such as shared management / staff / office / bank account)? Do you cooperate with any other companies in preparing offers or providing of goods or services? هل لديك شراكات مع أي من الشركات الأخرى ( مثل إدارة / الموظفين / المكتب حساب مشترك / البنك) ؟ هل تتعاون مع أي من الشركات الأخرى في إعداد العروض أو توفير السلع أو الخدمات؟ |
|
If the answer for previous question is yes, please provide details here including the names of partner companies. إذا كان الجواب عن السؤال السابق نعم ، يرجى تقديم التفاصيل هنا بما في ذلك أسماء الشركات الشريكة |
|
Other comments: ملاحظات اخرى: |
|
Experience / references for the related work of experience (Please attached any related contract, purchase order, certificate, etc.) that does not exceed 10 pages. References MUST include contact information. يجب ان يحتوي على عناوين الاتصال من مراجع الخبرة المرجع من الخبرة ( الرجاء ارفاق دليل من الاعمال السابقة ذات الصلة من عقود , اوراق شراء , ورقة اتمام عمل , اخرى ) لا تتجاوز عشرة اوراق. |
|
Signature التوقيع |
|
Date التاريخ |
|
Attachment No: 1
Scope of Work for Rehabilitation and Upgrading of Hand-Dug Well to Water Yard in Jokosti Village
Catholic Relief Services (CRS) – United States Conference of Catholic Bishops, an international relief and development agency, committed to the alleviation of human suffering, development of people and fostering of charity and justice in the world irrespective of race, creed, or nationality.
CRS seeks qualified entity specialized and experienced in water industry and construction of water systems (including water wells, water pumping components, solar energy set, elevated water storage and distribution pipework etc.) to work in Jokosti village in Central Jebel Mara locality (Golo) - Central Darfur State; the activities include rehabilitation of hand dug well, installation of submersible pump, solar energy unit, installation of elevated water tank and water pipework, and fencing of each component of the system, during the period from 17th March 024 to 15th May 2024.
Primary Functions:
Under the overall guidance and direct supervision of CRS WASH senior project officer (SPO), the contractor should rehabilitate, and upgrade one hand dug well to water supply, storage, and distribution system in line with technical guidelines of Water Environmental Sanitation Project (WES)-Sudan and CRS field staff.
The contractor responsibilities:
The specific tasks of the contractor under this scope of work should be implemented under direct supervision and instruction of CRS field staff, and each completed stage of the work should be accepted and approved by CRS field staff, and the contractor should implement and complete any required repair or amendment before starting the next stage. The work includes, but not limited to the following:
Bill of quantities and quotation:
No |
Item Description |
Unit |
Q’ty |
Unit price |
Total price |
1 |
Rehabilitation of hand dug well |
||||
1.1 |
Build and raise the top of the lining above ground surface by additional one meter should be built of red bricks and/or stones and cement-sand mortar. (the diameter of the well is 2.25 meters)
|
Job |
1 |
|
|
1.2 |
Construct a tight well-cover of reinforced concrete slab with a manhole to enable future cleaning and maintenance of the well. The reinforced cover of the manhole should be tight and leakage proof |
job |
1 |
|
|
1.3 |
Installing 2 steel beams at the top of the well to support the concrete cover, pumphouse casing, and hold the pump. |
job |
1 |
|
|
1.4 |
Install pump house, UPVC pipe and screen, from the top to the bottom of the well with diameter within range from 5 to 8 inches to properly fit the bowl size of the selected pump and allow suitable clearance for safe installation and retrieval of the pump. The top 6 meters of the casing and 2 meters at the bottom of the casing should be of blind (plain) casing and the portion in between should be of original UPVC screen of slot size range 0.04-0.06 inch |
m |
20 |
|
|
1.5 |
Clean the lining wall by using suitable long-handled wire brush to remove the algae and other dirt layers, then wash with high pressure water jet |
job |
1 |
|
|
1.6 |
Clean the bottom of the well, remove the sludge and all materials deposited inside the well at the bottom until all the original total depth is cleaned i.e. to remove at least 3.10 meters-thick layer of deposits from the bottom, to increase the current free depth from 12.90 m to 16 m (original depth). |
job |
1 |
|
|
1.7 |
Dewater the well until the turbid water completely discharged out and the turbidity level around 5 unit or less |
job |
1 |
|
|
1.8 |
Disinfect the well with high (conc.) chlorine dose applying shock chlorination processes according to the standard steps for chlorination. |
job |
1 |
|
|
1.9 |
Dewater the well and measure the residual chlorine |
job |
1 |
|
|
|
Sub-total (1) |
|
|||
2 |
Supply and Installation of Submersible pump and pipework |
||||
2.1 |
Import and install GRUNDFOS Electrical Submersible pump (complete with accessories) at setting depth 10 meter below ground surface inside the pump house (UPVC screen); the pump should meet the requirements mentioned above. |
no |
1 |
|
|
2.2 |
Provide and install high density polythene pipe of 2 inches diameter, and 225 meters long to connect the discharge point, at the well level, with the ascending galvanized (GL) pipe connecting the inlet of the elevated water tank with the supply line. |
m |
225 |
|
|
2.3 |
Excavate trench of one meter depth and 225 meters long extended from the water well to the elevated water tank and installing the water pipe; the rough portion of trench should be backfilled with 15 cm-thick sand/ or soft soil layer under the pipe and 25 cm-thick layer above the pipe then complete back filling of the remaining portion with the cutting excavated from the trench or alternative suitable soil materials. |
m |
225 |
|
|
|
Sub-total (2) |
|
|||
3 |
Supply and Installation of Solar energy unit and fencing |
||||
3.1 |
Provide and install complete solar energy unit with all accessories to properly operate the pump. (The solar unit should be installed at the specified area 30 meters away from the water well. Solar panels should be supported with heavy duty steel or galvanized skeleton and elevated at least 3 meters above the ground surface).
|
set |
1 |
|
|
3.2 |
Provide materials and construct tight fencing around the panels using heavy duty steal or galvanized poles (Angles or pipes) 3 meters high with spacing 2 meters or less, and barbed wire equipped with door and locks (the fencing area depend on the size of the solar unit that fit the selected pump by the vendor). |
job |
1 |
|
|
|
Sub-total (3) |
|
|
|
|
4 |
Supply and Installation of steal water tank and tower |
||||
4.1 |
Provide and install cylindrical steal water tank made of mild steel plates, of capacity 15000 liters, placed on steal tower 3-meters height, with accessories and the main requirement including, but not limited to what specified in scope of work hereabove. |
job |
1 |
|
|
4.2 |
Provide materials, fabricate, and erect steal tower of 3 meters height according to standard specification and guideline of Public Water Corporation (PWC). Including but not limited to specification in the scope of works hereabove.
|
job |
1 |
|
|
|
Sub-total (4) |
|
|||
5 |
Supply and Installing distribution pipeline 3”*2” diameter |
|
|||
5.1 |
Supply and install high density polythene pipeline of 3” diameters and 800 meters length and connect with the GL pipe descending from the elevated tank. |
m |
800 |
|
|
5.2 |
Supply and connect a 2”-diameters, 200 meters long high-density polyethene pipe connect with the 3” pipeline to supply water to the storage tank existing in the Health Facility, and the tap stand in Jokosti village. |
m |
200 |
|
|
5.3 |
Digging one-meter-depth and 1000 meters-long trench to accommodate the pipeline from the storage tank to the HF and tap stand. |
m |
1000 |
|
|
5.4 |
Back fill the rough section of the trench bottom (i.e. the portion with stone) back fill with sand or fine soil from the bottom up to 150 mm thick. |
m |
1000 |
|
|
5.5 |
Lay the pipeline in the trench and backfill with sand or soft materials up to 250 mm above the pipe then backfill the remaining portion of the trench up to the top i.e. ground surface with the cutting excavated from the trench or other available suitable source. |
m |
1000 |
|
|
|
Subtotal (5) |
|
|||
6 |
Construction of tap stand |
|
|||
6.1 |
Provide complete set of plumping materials and fittings for construction of tap stand of 12 taps connected to GL pipe equipped with gate valve. |
set |
1 |
|
|
6.2 |
Construction of the platform: the foundation of the platform should be of minimum 1.5 m width, 3 m long, and (0.3 m to 0.5 m) depth. The height of the platform 0.6 m, with 1.25 m height of the tap stand. |
job |
1 |
|
|
6.3 |
Provide and cover the top and sides of the platform with white tiles.
|
job |
1 |
|
|
6.4 |
Provide plumping materials and connect the tap stand with the water main line with 2” size high-density polythene pipe.
|
job |
1 |
|
|
6.5 |
Construct 2 meters high fencing around the tap stand with good quality wire mesh and 2”heavy duty Ukrainian steel angles, and gate door 2 m*2 m.
|
job |
1 |
|
|
6.6 |
Construct the floor of concrete slap 10 cm thick |
job |
1 |
|
|
6.7 |
Construct animal trough sized 0.6*0.6* 3 meters long outside the fencing area and 15 m drainage ditch from the tap stand to animal trough |
job |
1 |
|
|
|
Sub-total (6) |
|
|||
|
Grand Total* |
|
*The final cost of the work and settlement of the payments will be adjusted to the actual work done and materials provided, verified, and approved by the CRS field officers.
The vendor(s) can submit additional information or proposal with related prices (as suggestion) to replace or add to the existing BoQ lines while keeping quotation for the original BoQ as it is with relevant prices, and CRS will reserve the right to accept the vendor proposal fully, partially, or not.
Vender Name: Signature: Date: |
Stamp |