Construction of Infiltration Gallery Al Leri
Norwegian Refugee Council

The Norwegian Refugee Council is an independent humanitarian organisation helping people forced to flee. We work in crises in more than 30 countries, where we help save lives and rebuild futures.



 

 


 Bid No: PF-KRT-688 -Construction of Infiltration Gallery Al Leri
 City: Khartoum
 Deadline: 18 August 2022
 Description:

REQUEST FOR QUOTATION

 

Date: 14 Aug 2022

 

From:  

Norwegian Refugee Council (NRC)

Khartoum Country Office

 

Contact person:          Aseel Alnaw

Position:                      Procurement Assistant

Email:                          SD.procurement@nrc.no

           

Deadline for submission:     18th Aug 2022 @ 04:00 PM

 

All interested and eligible firms are requested to submit their offers by hand in sealed envelopes submitted to the address specified above or completed tender documents to be sent to electronic tender box sd.tenders@nrc.no

 

Subject:   

 

Construction of Infiltration Gallery in Um Koaro Village - Al Leri - South Kordofan

 

 

Requirements:

The office of the Norwegian Refugee Council invites your company to make a firm offer for the following items:

 

 

  • Please see ANNEX 1 – Scope of the Work.
  • Please see ANNEX 1 – Bill of Quantities.
  • Please see ANNEX 2 – Drawing / Design
  • Please input your prices in the table below - VAT INCLUSIVE.
  • Kindly sign and stamp your official Bid.

 

If you have any enquiries OR wish to schedule a site visit, please contact us at any time.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Annex 1: Scope of work & Building specifications:

Construction of Infiltration Gallery in Um Koaro Village - AL-Leri Locality & Accompanied of One Water Yard and installation of Solar powered pumping system

 

To reach the standard construction of Infiltration Gallery, tower elevated water tank and water point distribution. All necessary temporary works required to provide access to the site, secure storage of materials and to facilitate construction in a safe manner. All necessary site preparation works including the construction of a concrete foundation, the removal of top soil and subsequent backfilling, and all other ground and works that may be necessary. The Scope of Works shall also be deemed to include anything that is not listed here but may reasonably be inferred to be necessary for the completion of the Works.

Description: 

This is a scope of work document for Construction of Infiltration Gallery and accompanied of one water yard and installation of solar powered pumping system, water point distribution, Animal trough, and water irrigation channels in Um Koaro Village - AL-Leri locality - South Kordofan according to the specification and BOQ attached. Contractor shall supply all adequate and competent labours, supervision, tools and, equipment, installed and consumable materials, services, testing devices, and each and every item of expense necessary for Supply management.

Specification

In general, the contractor shall provide and maintain work environments and procedures which will safeguard the public and Government personnel, property, materials, supplies, and equipment exposed to contractor operations and activities; avoid interruptions of Government operations and delays in project completion dates; and, control costs in the performance of this contract. For these purposes, the contractor shall consider several factors of safety during implementation:

Health & Safety:

  • Laborers shall wear overalls and all the equipment safety measure for labors and must get instruction on the use of this equipment
  • Laborers shall have enough and appropriate tools and Keep maintenance materials back at least 600 mm (2 ft.) from the edge of any trench excavation and 1.2 m (4 ft.) from any other excavation. 
  • The water tank shall be protected from sunlight and covered at all the times.
  • Laborers shall make safe passageway to prevent slipping and tripping hazards.
  • All safety measures should be undertaken during COVID-19 pandemic.

 

 

Site preparation and planning:

 

  • Contractor shall coordinate with NRC WASH team, community representatives of Al-Leri urban area and Um Koaro village and the representative of Ministry of Infrastructure and Urban Development – Water Resource Sector to present the work plan include the supply materials and determination the site location for all the interventions.
  • Contractor shall advise on site use and improvements, selection of materials, water Yard system and equipment, as well as provide recommendation on construction feasibility, availability of materials and labor, time requirements for installation and construction
  • Contractor shall manage the activities of all interdisciplinary interfaces for the Work, including civil, structural, architectural, mechanical, piping, electrical, and instrumentation and controls.
  • Contractor shall provide construction site safety notices.
  • Contractor shall Breaking out hard material contained and cleaning the site.

 

Excavation and foundation work:

  • The contractor is responsible for digging the foundation plan area for Infiltration Gallery according to the BOQ.
  • The contractor is responsible for digging the foundation plan area for elevated tank according to the BOQ.
  • The contractor is responsible for planning before digging the foundations to conduct the centres of steel tower by accurate tools.
  • Contractor shall provide construction site safety notices.
  • The contractor digging the foundation properly until reach stable layer or add a compacted soil material.
  • The contractor shall provide bed sand for pipes and backfill the trenches and foundations after implementation.
  • The reinforce concreate should watering 2 times /day for 3 days.
  • The excavation shall be levelled properly, and compaction shall be by layers every 10 cm with compactable crushed granite, gravel, and aggregates coarse material.
  • Clean the area after the excavation and refill any loose soil around the foundation with improved soil. 

Concrete specification for foundation work:

  • Carry out the layout, dimension according to the dimension, which specified in BOQ.
  • Fix the footing of the steel foundation under the ground according to the specification in BOQ.
  • Treatment the concrete footing with water for at least 3days to achieve minimum of 30 N/mm2 after 28 days. The formwork shall be clean and fixed properly to ensure the stability of concrete.
  • Concrete shall be mixed properly to prevent segregation of concrete material. And infiltration of water or soil to the concrete material.
  • The surface of the reinforced concrete shall be smooth. The contractor shall be checking the foundation and materials before starting the reinforce concreate.
  • The Contractor should be aware about soil bearing capacity to ensure that the soil is able to carry the loads.
  • The Reinforce concrete cement ratio 1:2:4 with good watering (3 days).

 

Elevated stand steel foundation for vertical water tank:

  • Supply material and install the elevated steel tower with stair to be fixed on Reinforce concreate base, the steel tower includes six main columns, Height 3 m. The tower shall relate to slope members made from angle steel on top, center and down. The tower should be supporting a total Weigh  of 10,000 liter capacity and all loads. The surface of stand steel shall be made from smooth material to prevent cracking of the water tank. The tower includes Nuts, Bolts and painting the steel with anti-corrosive primer coat material. 
  • Provide good quality Paint for steel tower unit, the painting will be done in two to three coatings to ensure clean and adequate finishing.

 

Water tanks:

  • The contractor shall provide and install two plastic water tanks (5000 liters) good quality.
  • The water tanks shall be made from plastic material and shall be covered well and protected.
  • The water tanks shall be fixed on the top of the stand steel with 3.0 m height and shall be in a vertical form.
  • Water tank shall be made from Non-toxic material and the top cover of tank should not allow sunlight to enter the tank.
  • The Contractor should paint the tanks with orange color and NRC logo on the two side of tanks according to direction of the site engineer.

Pipelines:

Pipelines need to be laid: a supply line to convey water from borehole in Infiltration Gallery to the storage reservoir and distribution line to take the water from storage reservoir to the distribution points.

The pipeline needs to be protected to ensure a lifespan of 20 – years. Recommendations for laying pipelines include:-

  1. Preparing the trench: the nature of the ground will determine the choice of flexible or rigid jointed pipes .Flexible joints are preferred to rigid joints to allow for settlement which is likely .It is very important to ensure the alignment and bottoming up of the trench .Larges stone must be removed from the bed of the trench.
  2. Back filling all the trenches in hard formation need to be backed filled with 200 mm of sand or any soft materials especially where the ground is stony, the materials of the back filling must be soft and cannot contained lumps of rock or large stones .The pipe should be covered with a minimum cover of soft materials.
  3. Handling and laying of pipes: pipes must be handled with rope slings to preserve to protective coating and prevent puncturing which could lead to corrosion. Care must be taken, to ensure that the pipe ends ratline their circular shape. Upon delivery, every pipe must be inspected and rechecked before it is lowered into the trench.
  4. Testing pipes: Pipeline should be tested in reasonable length leaving the joints exposed to view. The test involves filling the pipeline with water under pressure, which exerts pressure of about 50% in excess of the working pressure. it could also be of extra pressure of known value say 30m to 50 water head

Galvanized iron (GI) Pipes

GI are usually supplied with tapered threads at the ends with one straight connector per pipe. It is preferable to cut the pipe to length with a pipe cutter rather than hacksaw.

To enable pipes and fittings to be removed for repair, threaded GI pipes should be joined with screwed unions on at least one side of a valve or fitting and in long length (>100m) GI pipes have flinched joints . Flinch dimensions can vary widely so new fitting must be carefully matched to existing pipe work. Ensure that there are sufficient gaskets for each flange joint. GI pipes can be welded, but this should be reserved for critical joints and for making up adaptors and special fitting.

Firmly anchor exposed GI pipes using pipe anchors of steel and concrete .Exposed empty GI pipes can became very hot in a warm and sunny climate. Care must be taken when filling hot pipes with cold water as the sudden contraction can damage threaded joints causing them to leak.

The following precautions should be taken when handling and storing GI pipes:

  • Protect the threads in transit and when loading and unloading as they can be easily damaged. A new GI pipe is normally bundled with a straight connector on one end and thread protector on the other
  • In transit ensure connectors are firmly screwed on each pipe as they can vibrate loose.
  • In hot, sunny conditions, store a GI pipe under cover as pipe may become too hot to handle.

Installation of submersible pump unit:

 

  • The contractor will be responsible for providing expert Engineers and technicians for installing submersible pump.
  • The contractor shall Provide and check truck Crane and all accessories before installing submersible pump unit in suitable depth, based on the attached pumping test report and the materials should be test before installing.
  • The contractor shall secure the Borehole after installing submersible pump unit by covering the top of well.
  • The contractor provides on-going report engineering support through completion of the Work.

Construction of distribution point:

 

  • Distribution point should be able to accommodate Um Koaro water users, humans, and small livestock. Arrangement of all these to distribution points should facilitate water collection for the users and water supply provider. Distribution points are demonstrated.
  • Maxing ratio of concrete according to BS.
  • The contractor should construct one water stand for humans with wall and concrete slap and raised at 1.0 m wall with 10 taps I inch, 5 taps in each side with high quality according to attached BOQ and direction of site engineer.
  • The contractor shall install a drainage system and plain concrete around water distribution points if needed.

 

Installation of solar system:

 

  • The contractor shall provide a total of xx Solar PV-Module poly crystalline of 180 -200 Watts, or equivalent to the total power demand with junction box. The panel should have a period of warranty of up to 10 years.
  • The contractor should provide inverters with good quality and warranty for at least 2 years.
  • The solar panels should be placed, and spot welded in an elevated position with a height of at least 4- 5m of the generator room to avoid stealing and damaging using beams 14 mm and heavy angles, 15-tilt angle with high stand and high wind speed (50km/h) the support fixed into line.

 

Construction of the Generator room and fencing:

  • Size 3x3x2.5, the contractor shall fabricate and install 2 windows made with both expanded good quality metal and 30-gauge zinc sheet. The generator room should have one steel door and plain concrete floor (1:2:4) 10 cm thick. The room should be constructed for simple assembling and dismantling, and the generator should place on foundation 20 cm above the floor level.
  • The solar panels should be in the top of the generator room according to BOQ and instruction of site engineer.
  • The contractor should ensure that the generator room would be able to carry the loads of the solar panels stands, using beams on the four angles and heavy angle for solar panels stand.
  • Construction of fencing for the Water Yard and the three Water distribution points.

 

  1. GENERAL NOTES:

A1) MATERIALS AND WORKMANSHIP

All the work noted in this specification must be carried out to the highest standard which is normally possible, using only the best materials and most skilled workmen. Samples of all construction materials must be shown to a representative of NRC for written approval before starting construction. The contractor should pay his team and NRC will not be answerable to contractor’s failure to meet his contractual obligations with his employees.

A2) SITE IN CHARGE

The CONTRACTOR must employee an experienced site-in-charge who must be on site to supervise the work at all times when work is Generally leave the whole area of the site clean, washed, tidy and ready for use.

 

  1. BASIC MATERIALS:

B1) CEMENT

The choosing of cement brand must agree with a representative of NRC. All cement brought to the site must be fresh (manufactured within previous three months) and in perfect condition for use. All cement brought to the site must be stored carefully so that it remains in perfect condition. Storage must be a totally dry place with a platform of planks or bamboo to keep all cement 6” minimum height above the ground.

B2) COARSE AGGREGATE FOR CONCRETE

The first choice of coarse aggregate chosen by NRC is graded mountains gravel of suitable type and strength. The second choice of aggregate is broken stone of suitable type and strength. The source of aggregate should be clean and free from impurities and plant material. The shape of the aggregate should be mostly rounded with a small number, which are long or flat. If this type of aggregate is not available the CONTRACTOR must agree with a representative of NRC which other type to use.

B3) SAND

The sand must not contain mud, dust, or pieces of plants. The CONTRACTOR must make all efforts to obtain coarse sand (with zero fines). A sample of sand must be shown to a representative of NRC. For plastering, the sand must be sieved according to the NRC site Engineer’s additional specification.

 

B4) WATER

Clean water should be used in all construction works especially for plaster or mortar. The CONTRACTOR must inform a representative of NRC as to the source of water used in all construction works.

 

C) WORKMANSHIP:

       C1) CONCRETE WORKMANSHIP

All materials for concrete (cement, sand, aggregate and water) must meet the quality specifications set out in Section B above. The proportions of cement, fine river sand and aggregate must be determined by volume according to the following table:

Concrete Mix (1m3)

Cement

River Sand

aggregate

1:2:4

kg

m3

m3

1:3:6

kg

m3

m3

 

Water/cement ratio quantity of water must not to exceed the following:

 

Concrete Mix

Amount of water

1:2:4

32 litres per 50kg cement

1:3:6

25 litres per 50kg cement

        C2) WELDING WORKMANSHIP

  • Contractor should provide the suitable welding machine and the machine shall be in adequate capacity to support the energy requirement for the work. Filler materials, electrodes, and wire should be provided by the welder, and it should achieve the standard quality. The Welded area should be contoured to permit complete fusion at the sides of the bevel and to minimize slag inclusions.  Flux and slag should be completely removed from weld beads by policing and from the surface of completed welds and adjoining base material.  The flux removal should be done in a manner that will not contaminate or overheat the weld or adjoining base material. Weld reinforcement and finish with appropriate paint should be as required by the NRC representative. Undercutting of the base metal or roof material is not permitted. Welding process shall be free of cracks, cold lap, excessive porosity, slag inclusions, and other defects indicative of poor workmanship
 

 

Annex 2: Construction of Infiltration Gallery in Um Koaro Village - Al Leri - South Kordofan

 

 

BILL OF QUANTITIES

Construction of Inflitration Galley in Um Koaro Area - Al Leri - South Kordofan

1

GENERAL INSTRUCTIONS

By populating and pricing the BoQ items below, the tenderer certifies and confirms his complete acquatintance with and understanding of the site conditions, scope of work, designs, sepecifications, BoQ, the prevailing market conditions and the local laws and regulations. All and any other items not priced hereunder shall be deemed part of the unit rate pricing all works should be done according to the code of practice, engineering standards and the instruction/ satisfaction of NRC

2

MASONRY INSTRUCTIONS

The work include supply material and construct masonry works, the supply of material include red cured bricks, stones, cement, sand, gravel, reinforcement steel, water,  all water supply equipments, skilled and unskilled labours, etc.., and curing after building and any other work requirements, all works should be done according to the insruction of NRC

 

Ref

Title

Item(s)Description

Unit

Quantity

Unit Price

Total Price

1

Site preparation and preliminary work

 

1.1

Site Preparation of infiltration gallery area

Removal breaking out of hard material on site, cleaning the vegetation, roots of plants, clay soil in infiltration area and debris from the site at least 100 m on the surface area. The cost includes checking the distance & verifications of the horizontal and vertical alignment of the proposed location.

Job

1

   

1.2

Site Preparation for the tank installation/construction area and distribution point areas

Removal breaking out of hard material on site, cleaning the vegetation, roots of plants, clay soil in tank construction area and debris from the site at least 100 m on the surface area. The cost includes checking the distance & verifications of the horizontal and vertical alignment of the proposed location.

job

1

   

 

2

Construction of Infiltration Gallery

                                           

2.1

Construction works at the location of the Main Body surface area

                                            

2.1.1

Excavation work - including de-silting of accumulated silt

Excavate and cast away loose soil and silt, debris and other unwanted materials from main body foundation with width thickness of 2m, length 10 m and depth 2m depending on soil condition, excavated soil should be transported away from the construction area by at least 100 m distance, the excavation can be increased or decreased according to the condition of the soil as specifications and engineer instructions

M3

40

   

2.1.2

Foundation work

Supply construction materials(sand, cement) to attain a mixing ratio of 1:3 cement : sand mortar stone on depth 2m to the ground level according to soil condition, thickness 2m, length 10 m

M3

40

   

2.1.3

Construction work

Supply construction materials(sand, cement) to attain a mixing ratio of 1:3 cement :  sand mortar stone on height 1 m from the ground level, thickness 0.7m, length 10 m

M3

10.50

   

 

2.2

Construction works at the location of the Wings structure area

 

 

 

 

                                            

2.2.1

Excavation work including de-silting of accumulated silt - foundation level

Excavation and casting away of loose soil and silt, debris and other unwanted materials to provide some space for the wing structure foundation with thickness 1m and lenght 10 m depth depending on soil condiction, excavated soil should be transported away from the construction area by at least 100 m distance, the excavation can be increased or decreased according to the condition of the soil as specifications and engineer instructions

Job

1

   

2.2.2

Foundation work - below ground level space

Construction of the foundation works with the supplied materials (sand, cement) to attain a mixing ratio of 1:3 cement : sand mortar stone on depth 2m to the ground level according to soil condition, thickness 2m, length 10 m. In rate shall includes all needed maerials and workmanspips (cutting, bending, curing,…,etc) according , specification and NRC standards

job

1

   

2.2.3

Construction work - Wings

Construction works including, cast and buliding reinforecd concrete foundation with supplied materials(sand, cement) to attain a mixing ratio of 1:3 cement :  sand mortar stone on height 1.5 m from the ground level, thickness 0.7m, length 10 m, wall  rate shall includes all needed materials and workmanships (cutting, bending, plasering, curing,…,etc) according to drawings, specification and NRC standards

job

2

   

3

Construction of gabion section area above and below water level

 

       

3.1

Excavation work including de-silting of accumulated silt for the gabion section area

Excavate and cast away loose soil and silt, debris and other unwanted materials from the main body foundation with thickness 1m and lenght 10 m depth depending 3m on soil condition, excavated soil should be transported away from the construction area by at least 100 m distance, the excavation can be increased or decreased according to the condition of the soil as specifications and engineer instructions.

 

 

m3

30

   

3.2

Foundation work for the gabion section area

Construction of the foundation works for the gabion section with the supplied materials (sand, cement, stones) to attain a mixing ratio of 1:3 cement: Gravel will be provided to act as filters, while sand mortar stone for the specified depth. Total height is 3 m(2m will be under water, while 1m depth will be above the water surface). thickness 0.7m, length 10 m. In rate shall includes all needed maerials and workmanspips (cutting, bending, curng,…,etc) according , specification and NRC standardsexcavate and cast away loose soil and materials

 

 

m3

25

 

 

 

 

 

 

 

 

4

Infiltration well construction works

 

 

 

 

                                            

4.1

Excavation of the walls for the infiltration well within the dam area, located near the gabion structure area

Excavate and cast away loose soil and materials for the infiltration well structure foundation with diameter 2m and depth 3m depending on soil condition, excavated soil and debris should be transported away from the construction area by at least 100 m distance, the excavation can be increased or decreased according to the condition of the soil as specifications and engineer instructions.

m2

6

   

4.2

Construction work - lining of the well from botton to top, with provision for water infiltration.

Construction of the well lining using the supplied materials (Red bricks 25cm*16cm*6cm  fully cured and of good quality, Gravel pack, cement and building bars ( 1.5RB). This materials will be used in the construction of the internal wall lining,  the well will be of 3m height, with porous pipes laid horizontally to transport water into the well open space. Gravel fIlters will also be installed in the annullar space bewteen the well lining and the wall..

job

1

   

4.2

Shallow well construction work reinforcment  - well head at the top of the well from, with provision for access into the well. This will act as the cover to the well top area.

Construction and supply materials, cast, building plain concrete with thickness 0.2m in  reinforecd concrete foundation in 1:2:4 mortar, foundation reinforcment is 12@200 c/c in both way rate shall includes all needed materials and workmanspips (cutting, bending, curng,…,etc) according  specification and NRC standards

job

1

   

4.2

Supply of gravel for gravel packing to 2.5 m depth in the infiltration well and cement grouting in the remaining space above the gravel 0.5m length.

The gravel to be provided for the shallow well is calculated at 1.256m3, appx 1.5 m3. this means one truck of two tonnes is required to supply the gravel of dimensions 2-4 mm size.

m3

1.5

   

4.3

Digging trench from the infiltration well to the location where the storage tank will be installed. This will be 50 m length.

Digging trench length 54m, width 0.40m,depth 0.4m .The trench shall be backfilled by  original after pipelaying installing the pipeline .The cost include  backfilling the trench and leveling the ground surface to a smooth surface.

m

50

   

4.4

Procurement and installation of the rising main Pipes. 6 Pieces GI Class B and 52 metres length HDPE 10 bar. The pipes will be for the distribution main pipes. This should include accessories/fittings, threadsils< sockets, grease (3 pipe bends, and adapting sockets 2" diameter).

Supply and Install galvanized class B rising main pipes (6 GI PIPES)diameter 2 inch with sockets. The pipes  are of 3 m length and shall be connetcted from the submersible pump setting to the water tank .The rising pipes on the ground shall be layed inside the trench. The rising pipes Approximately 3m for the well ,the cost includes valve,fitting  and all  accessories. The distribution main will be 52 m HDPE bar 10 pipe with adapting sockets.

m

70

   

4.5

Submersible Pump - SP 11-3, 0.75 KW, Speed for pump data: 2900 rpm, Rated flow: 11 m³/h, Mains frequency: 50 Hz, Rated voltage: 1 x 230 V, Rated current: 7.45 A, 4mm cable size.

Supply and Install submersible pumps Good quality with guarantee. The inside dimeter of the construeter well 1m .The pump should be install according to soil condition. The submersible pump  specifications 2 inch D, yield 10 to 15 m3/h and total head 8m mother cost includes pump drop cable size to suit electric requirement of the motor, using GL pipe to install the pumps equivalent to the digging well depth. The price should include 60 m lenght pump cable pricing to the generator.

set

1

   

 

5

Construction elevated water tank

                                            

5.1

Foundation works for the elevated tank

6 isolated reinforced concrete footings 1x1x0.5m, 2 m c/c with 0.1m, plain concrete under the footing. Short columns 0.5x0.5x0.7m ( subject to site conditions ).Tie beams 0.3x0.3m. Excavation depths maybe subject to increase or decrease according to site condition. Concrete mix proportion is (1:2:4) for plain concrete.

job

1

   

5.2

Supporting steel tower - with reinforcements.

The steel tower height is  4m with strong tower to support 22,500 liters of water plus the weight of the steel tank 2m. The branch beam should be of IPE 160x80mm, main beams (architrave) of IPE 180x90mm. The stations should be one bay with a total height of 4.0m manufactured from IPE 200x100x22 kg/m. All wind bracings should be Manufactured from 65x65x3 mm mild steel angles whilst the horizontal brace at the middle of the tower is from 80x80x65mm  mild steel angles , all braces connected with Ø 16x50mm bolts and washers. The thickness of the foot plate and top plates should not be less than 12mm, whilst that of the gusset plates thickness should not be less than 6mm. A total of 20 holding down bolts, nuts and washers should be supplied in adequate sizes but not less than 22mm  Ø and 500mm length,2 anchor bolts are to be used per footing.

Job

1

   

5.3

2 Elevated PVC water tank with ball valve and outlet, inlet and wash out provisions

Supply and install 2 PVC water storage tank  10,000 liter(Good quality). The tank shall be fixed on the top of the steel foundation. The tank shall be made from  Non-toxic material, resistant to abrasion and corrosion. Temperature resistant and UV light resistant. The cost includes all the necessary accessories for fitting, with painting the tanks externally with Orange color and NRC logo in both sides of the tanks. The tank pricing will include 4 m pipe lenght for the outlet side of the tank.

Job

1

   

 

6

Distribution water pipelines to the water collection points

                                            

6.1

Labour works on trench digging

Digging trensh length 950m, width 0.40m,depth 0.4m. The trench shall be backfilled by  original soil after pipelaying installing the pipeline .The cost include  backfilling the trench and leveling the ground surface to a smooth surface. The distribution points will be three for human water point collection, and another 2 going to the location of animal troughs

m

950

   

6.2

Supply and installation of the Pipes in the trenches

Supply and laying of 2" inch HDPE pipe 950 meters lengh, as pipe line to convey the water from water tanks to the three water collection points and one animal water drinking point. The cost including necessary fitting and fixation.

m

950

   
 

7

Constriction of tapstand points and animal trough

                                            

7.1

Construction of water tap points

Construction of water tap points with 10 taps, 5 taps in each side using heavy duty and easy to use. The taps point fixed to concert slap raised at 1.0 m wall with smooth concerte slap,drainage system.

No

3

   

7.2

Water trucking other means of water collection and Distribution Point, location near the tank outlet point

Construction of one donkey water trucking or collection point using 2 inch GL pipe and 4 m green hose with good quality and building of good drainage system.

job

1

   

7.3

Construction of animal trough

Manufacturing 2 animal trough should be from iron sheet 3ml and original heavy angel  assad factory 2 inch, with 2 valve controller 2 inch and lockable on service concrete 10cm over ground 

job

1

   

 

8

Constriction generator room and installation of solar system

                                              

8.1

Generator equipment

Provision and installation Generator engine (Shana or Jandong) 18 HP, 7.5 watts  with all the accessories. 14 kva

job

1

   

8.2

Construction of generator room near the elevated PVC  tank location.

Supply materials and construct generator room from Zink sheet, Size 3x3 m x 2.5 m height at the front side and 2.7 m height at the back with squire pipe 3X6 cm 3mm thick for roof and beams 14 mm for the corners( height 3.5 at the front sid and 3.70 m at the backe side, for solar stand). Fabricate and fix 2 windows 120X120 cm made with both expanded metal and zinc sheet. The generator room should have one steel door 1X2 m and plain concrete floor (1:2:4 mix) 10 cm thick. The room should be constructed for simple assembling and dismantling. The generator should be placed on foundation 20 cm above the floor level.

job

1

   

8.3

Solar Panel

Provision and installation polyenstalline 250 watt, good qauilty ,the solar shall be matched with submersable pumps ,Provide control box for operating the solar system ( off/on ),the cost includes provsion of alternator, water level wire, inventor, connection box, cables and all necessary materials to be fixed and safty. The supported structure for the panels should be on the top of the generator room using beams 14 mm and heavy angles 2 inch , the stand slop 15 degrees-angle and high stand up to 1.0m above generator room.

set

10

   

 

9

Protection and light system

                                             

9.1

Construction and fencing of the gabion fence, chain link type around the water tanks and generator room.

Construction, chain link tpe of fence (3 mm) ,15x15 with total  height 2m, distance  between every two pipes(2") 2m, Dig base 50 * 50 * 40 cm for fence posts. Tightening wire gabion with three loops of tension wire and create a frame from the angle of 2 inches 1.7 mm araund the fence with good fixation according to the originals of manufacture. Manufacture and installation of a 2* 2 m door from heavy  2-inch angle and mesh, and making Orange paints for the menus, the frame and the door according to the directions of the supervising engineer. and build 0.3m wall  arround the fence.

Set

1

   

9.2

Construction and fencing of the gabion fence, chain link type around the distribution points

Construction, chain link tpe of fence (3 mm), 5mx5m with total  height 2m, distance  between every two pipes(2") 1,5 m, Dig base 50 * 50 * 40 cm for fence posts. Tightening wire gabion with three loops of tension wire and create a frame from the angle of 2 inches 1.7 mm araund the fence with good fixation according to the originals of manufacture. Manufacture and installation of a 2* 2 m door from heavy  2-inch angle and mesh, and making Orange paints for the menus, the frame and the door according to the directions of the supervising engineer. and build 0.3m wall  arround the fence.

No

3

   

9.3

light system

Provide and install light system in sound round the inflitration galley, and in distrbution points areas and the light should be connect with the solar system and generator, the light system should be have capacity to work more then 10 hours per day,  The cost includes all the necessary accessories for fitting.

set

4

   

9.4

Singboard

provide and install singboard 2*1 from one and a half pipe and steel sheet with height 2.5 form ground level, the cost included the foundation work, plain, and witting the project details according to NRC instruction.

set

2

 

                                              

#

 Total Cost:

                                               

 
        1. 3 – Drawing / Design

 

 

 

 

 

 

 

 

 

2- IMPORTANT NOTE:

 

You can use the above table

OR you can print your quotation on your own letter-head documents.

 

Your quotation shall be printed, signed and stamped.

Don’t forget to include your company name, address, contact details as well as your tax number.

 

Prices must include VAT (in prices or in total).

If different taxes & fees apply, please specify them all in your quotations and include them all.

 

Important Remarks:

  • Sub-contracting and Joint venture can be accepted. The contractor must include the name, and company profile of potential subcontractors or partners.

 

 

Warranty period & Defect liability guaranty:

A warranty period of 120 days will be observed. This period will start the day following the reception of the completed work. During the warranty period, the contractor will be obliging to resolve / correct all defects notified to him by NRC.

10% of the total value of the contract will be retained by NRC to cover the warranty period.

The retained amount will be paid once all defects (if any) have been corrected, and within 15 days after the end of the warranty period in case no defects were notified to the contractor.

 

 

 

 

 

 

 

 

 

 

 

 

3 - Please answer the questions:

Questions

Answers

What is the currency of the offer?

(SDG, USD, other…)

Note that NRC will favour quotes in USD. Please read below regarding USD payments.

 

DO NOT PROVIDE QUOTES IN BOTH SDG AND USD CURRENCIES.

 

Please confirm your offer inclusive Net price after deduction of discounts

 

Please confirm your prices include all taxes and fees (net prices) :

(if not, please explain and detail the taxes & fees)

 

 

If your offer is in USD => payment will be made by bank transfer.

  • Do you have a USD account in Sudan ? if YES, then in which bank.
  • Do you have a USD account abroad ? if YES, then in which bank.

(please provide bank details for each account)

 

Please read the note below regarding payments in USD and quote accordingly.

 

 

Do you accept payment after completion of work?

(if not, please explain your payment terms upon milestone completion)

 

 

What is the validity period of your offer?

(in days)

(Preferable 60 days)

 

 

Please confirm that you will be able to transport all the necessary machines to the site locations, and that you will ensure the security of your equipment once on site.

 

Your company and all your workers must commit to respect the population and to follow the rules and regulations implemented in the site, especially regarding safety and security, and employment =

By submitting a quote, you confirm your commitment

 

Please confirm that your company have the necessary insurances to protect your employees, your equipment, the work site and any third party.

 

Please confirm you can deliver to our address in :

Um Koaro Village - Al Leri - South Kordofan

 

 

4 - Accepted methods for submission of quotation / offer :

 

We recommend you to fill up this Request for Quotation directly on your computer.

You can also print it and fill it up by hand if you have not access to a computer.

You can submit the price offer by using the table on page 1, or by using your own proforma document.

 

  • By hand delivery to NRC Office, Address: The Nile Tower, Fourth Floor Block 10, Building #20, Street 63, Khartoum – Sudan
  • OR by email to the electronic box: sd.tenders@nrc.no

 

Your quotation / offer must be signed and stamped on all pages (including the present Request for Quotation).

 

IMPORTANT NOTE regarding USD quotes and payments :

 

  • You must choose between quoting in USD or quoting in SDG.
    • Do not provide quotes in both currencies. If you do so, only your quote in USD will be considered for assessment.
  • If your quote is in USD, then you will be paid in USD.
    • You must be in capacity to accept the payment.
  • NRC will favour payment in USD, in Sudan, in the same bank.
  • NRC has USD bank accounts in :
    • Blue Nile Mashreg Bank
    • United Capital Bank.
  • For payment within Sudan, you must have a bank account in one of the same bank as NRC.

 

We encourage you to contact us directly if you have questions or need clarifications before submitting your quotation.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

4 - Your Company details:

  • General information

 

Name of the company

 

 

 

Name of the owner(s)

Date of birth of the owner(s)

(mandatory for screening)

 

 

Address of the company

 

 

 

Name of contact person

 

 

 

Position

 

 

 

Email

 

 

 

Phone

 

 

 

 

 

  • Company bank account details:

 

Beneficiary name:

  

 

Beneficiary account no.:

 

 

Beneficiary Bank:

 

 

Bank branch:

 

 

SWIFT:

 

 

IBAN:

 

 

Bank address:

 

 

 

  • References 

Please provide details of at least 3 client references whom NRC may contact, preferably from NGOs and UN agencies, for similar related works:

 

Client/company name

Contact person

Phone

Email

Contract details (works, location, size, value, etc)

1.

 

 

 

 

2.

 

 

 

 

3.

 

 

 

 

 

 

 

 

 

  • Equipment

Please provide details of any relevant machinery/equipment/vehicles owned by the company that would potentially be used for construction: (do not mention rented items):

 

Type of machinery/ equipment/ vehicles

Quantity

1.

 

2.

 

3.

 

4.

 

5.

 

6.

 

 

 

 

5 - Mandatory documents to attached to your quotation / offer :

 

Please check that you are providing all of the below mentioned documents:

 

Mandatory documents

Checked (Y/N)

Copy of renewed business license – Compulsory

 

Copy of VAT registration – Compulsory

 

Company tax registration certificate – Optional

 

Availability of Machinery Trucks - Compulsory

 

Past contracts/ POs as proof of experience for similar contracts – Compulsory

 

Previous experience in same locality or South Kordofan – Compulsory

 

Financial Statement from your bank for the last two Year – Compulsory

 

Detailed delivery schedule - Compulsory

 

Company Profile – Optional

 

NRC Request for Quotation (filled up, signed and stamped)

  • You can use the RFQ table above
  • Or any other format of your choice, but specifying all items in the RFQ list.

You must Sign and Stamp each page.

 

 

 

You can also attach additional documents such as photos, company profile, certifications…

 

6 - Payment information:

 

For payment by cheque, please indicate under which name NRC shall issue the cheque. You can write name in Arabic or in English. (For Payment in SDG)

 

 

 

 

 

7 - Other information:

 

Payment will be made by bank transfer/cheque only.

 

All suppliers doing business with NRC should maintain high standards on ethical issues, respect and apply basic human and social rights, ensure non-exploitation of child labour, and give fair working conditions to their staff. NRC reserves the right to reject quotations provided by suppliers not meeting these standards.

 

Vendors doing business with NRC will be screened on anti-corruption due diligence before NRC confirms an order or contract.

 

NRC aims to purchase products and services that the minimum environmental impact. Environmental considerations form part of the NRC selection criteria, and NRC reserves the right to reject quotations provided by suppliers not meeting these standards.

 

NRC is obliged to ensure that its procurement decisions are clearly justified and documented and keeping within the Donors mandatory principles. In that regard, full and on-the-spot access must be granted to representatives of NRC, the Donor or any organisation or person mandated by it, to premises belonging to NRC or its contractors. The right to access shall include all documents and information necessary to assess, or audit the implementation of the contract

 

NRC reserves the right to accept or reject the whole or part of your quotation based on the information provided. Incomplete quotations which do not comply with our conditions will not be considered.

 

Shortlisted suppliers may be required to submit samples of each item. Please be sure to have all samples available at short notice, and wait for a response from NRC if you have been shortlisted.

 

 








Copyright (c) Sudanbid.com, 2019-2024. All rights reserved